Project Description:
BOXFORD- MERRIMAC- PEABODY- BRIDGE PRESERVATION- B-19-010, B-19-012, M-16-006, P-03-027, P-03-037 & P-03-051
This project will perform a series of bridge preservation activities including wearing surface replacement, deck repairs, joint replacement, substructure repairs, steel repairs and painting.
Location:
  • Town of Boxford
  • Town of Merrimac
  • City of Peabody
  • Construction Begins: Spring 2023
    Resident Engineer: Richard Apitz
    Construction Bid Price: $11,458,783.10
    District: District 4
    Current Status: Contractor began excavating concrete haunches and installing timber shielding at Bare Hill Road Bridge. (as of 01/08/2024)

    Contracts (2) Progress
    # 115795 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 121027 -- Construction Contract
    Bridge Repairs and Related Work (Including Painting) Br. Nos. B-19-010, B-19-012, M-16-006, P-03-027, P-03-037 and P-03-051 over Interstates 95 & 495 and Route 1 54% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 04/22/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Contractor began excavating concrete haunches and installing timber shielding at Bare Hill Road Bridge.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/08/2022
    Project Initiation Form PIF Entered 09/14/2022
    Project Initiation Form PRC Submitted 09/14/2022
    Project Review Committee PRC Approved 09/15/2022
    Project Status Advertised 12/24/2022
    Project Management
    100% Design 100% Package Received 11/16/2022
    100% Design 100% Package Comments to DE 12/02/2022
    Final Design PS&E Received 12/09/2022
    Final Design Peer Review Comments to DE 12/21/2022
    Final Design PS&E to FAPRO 12/12/2022
    Final Design PS&E Received - Resub 1 12/23/2022