Project Description:
DISTRICT 5- OFF-SYSTEM BRIDGE BUNDLE, D-14-008, L-01-011, L-01-015, M-03-018, P-13-031, P-13-035, W-06-038 (DB)
This is a design-build project for eight bridges located in District 5. These bridges carry East Street over Route 3 in Duxbury, Pickens Street over Route 140 in Lakeville (2 bridges), George Street and the MBTA/Amtrak over Copland Drive in Mansfield (2 bridges), River Street over Plymouth Plantation Highway in Plymouth, and Jordan Road of Route 3 in Plymouth (2 bridges). The work to be done under this Contact consists of demolition of the deck and replacement with new concrete bridge deck with updated railings and new bituminous wearing surfaces, substructure repairs, cleaning and painting of structural steel and structural steel repairs. The work will also include the application of an elastomeric protective coating to concrete surfaces at the piers, abutments, and copings. The scope of work also includes maintenance of traffic during all operations according to the Temporary Traffic Control Plans.
Location:
  • Town of Duxbury
  • Town of Lakeville
  • Town of Mansfield
  • Town of Plymouth
  • Town of Wareham
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2023
    Project Manager: Marco Pereira
    Estimated Total Contract Cost: $33,968,568.60
    Estimated Total Federal Participating Construction Cost: $35,254,085.15
    District: District 5
    Current Status: This project has been advertised for construction bids. (as of 04/15/2023 )

    Contracts (1) Progress
    # 87750 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 5. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/08/2022
    Project Initiation Form PIF Entered 09/13/2022
    Project Initiation Form PRC Submitted 09/13/2022
    Project Review Committee PRC Approved 09/15/2022
    Project Status Advertised 04/15/2023
    Project Management
    25% Design 25% Package Received 04/05/2023
    Final Design PS&E Received 04/05/2023