Project Description:
HAVERHILL- WEST NEWBURY- BRIDGE REHABILITATION, H-12-020=W-20-004, MAIN STREET OVER THE MERRIMACK RIVER (ROCKS VILLAGE BRIDGE)
The proposed project consists of rehabilitating or replacing movable bridge components of the Main Street Bridge over the Merrimack River. Work includes replacing concrete and timber decking with FRP deck, replacing selected floor beams and stringers, replacing selected gusst plates, adding a traffic railing on the bridge and minor approach roadway work.
Location:
  • City of Haverhill
  • Town of West Newbury
  • Resident Engineer: James Gruttner
    Construction Contract Value: $14,072,433.00
    Construction Bid Price: $11,578,724.50
    Initial Construction Estimate: $13,115,705.67
    District: District 4

    Contracts (6) Progress
    # 54828 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open basis for various statewide highway and bridge projects. Final
    # 54833 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57464 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 57467 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 57915 -- Design -- Services
    Work will consist of providing engineering design services to the MassHighway on an open end basis for Layout and Right of Way assignments. Final
    # 70720 -- Construction Contract
    Bridge Rehabilitation (Including Painting) (H-12-020=W-20-004) (Steel) - East Main and Bridge Streets over the Merrimack River (Rocks Village Bridge). (ABP). Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/21/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/06/1979
    Project Status Advertised 08/27/2011
    Project Management
    25% Design 25% Package Received 07/09/1995
    25% Design 25% Package Received 08/23/2010
    25% Design 25% Package Comments to DE 11/24/1995
    25% Design 25% Package Approved 06/26/1996
    25% Design Design Public Hearing 06/26/1996
    25% Design Design Public Hearing 04/28/2011
    25% Design 25% Plans Complete 06/26/1996
    75% Design 75% Package Received 05/03/2011
    Final Design PS&E Received 06/27/2011
    Final Design PS&E Received 08/19/2011
    Final Design PS&E to FAPRO 08/23/2011
    Consultant Contract Process NTP Issued 03/09/1995