Project Description:
DISTRICT 5- SAFETY IMPROVEMENTS AT VARIOUS LOCATIONS
The project will improve safety for all road users by implementing short-term safety improvements at various targeted locations to be determined. Improvements may include signage, pavement markings, improving existing crosswalks or installing new crosswalks, signal timing updates, curb extensions, etc. This project is being initiated for mainland with a preliminary list of projects included below: Corridor-wide systematic improvements: -Implement passing zone closure per District Traffic Section recommendations -Barnstable Route 6A - review speed posting and signs (coordinate with HQ) -Scituate Route 3A - evaluate data from temp trailers and for possible permanent installation of speed feedback signs (Henry Turner Blvd to First Parish), tree trimming for visibility Specific locations: -Fairhaven - Benoit Square (Main St/Adams northern intersection at square, review signal timing at Main/Adams/Howland) -Marion - Rte 105/Front St: review for exclusive left turn on Rte 6 and other short term improvements -Rehoboth - Rte 6/Barney Ave evaluate constructing an island to restrict left (create right in right out), tree trimming -Easton - Rte 138/Turnpike St: better channelization of Rte 138/Turnpike intersection -Bourne - Rte 28/Waterhouse: investigate stop instead of yield -Hanover - Rte 53/139/Broadway (Top 200): install back plates, adjust all red clearance, review traffic signal operation -Hanover - Rte 139/Grove St: Right-in/right-out (coordinate with Town, who may implement prior to this project) -West Bridgewater - Rte 28/Matfield - delineate intersection with curbing, improve ped accommodation across Rte 28 -Bridgewater - Rte 28/18/Grove St: review lane assignment, review one way in/out of Grove St -Scituate Roundabout: signage, pavement markings, concrete truck apron
Location:
Design Responsibility: Consultant
Right of Way Responsibility: MassDOT
Project Manager: Koby J Lemrise
Estimated Total Contract Cost: $4,379,616.55
Estimated Total Federal Participating Construction Cost: N/A
District: District 5
Current Status: PS&E Received (as of 04/02/2024 )

Contracts (0) Progress
No contracts associated with this project

Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/15/2022
    Project Need Form PNF Approved 08/31/2022
    Project Initiation Form PIF Entered 09/15/2022
    Project Initiation Form PIF Approved 08/31/2022
    Project Initiation Form PRC Submitted 09/15/2022
    Project Review Committee PRC Approved 09/15/2022
    Project Management
    100% Design 100% Package Received 11/13/2023
    Final Design PS&E Received 04/02/2024