Project Description: |
ORANGE- WENDELL- DECK REPLACEMENT, O-03-025=W-15-012 (0VX), STATE ROUTE 2 OVER COMB STATE ROUTE 2A, MILLERS RIVER AND WENDELL DEPOT ROAD
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | Thomas H Currier |
Estimated Total Contract Cost: | $11,937,240.00 |
Estimated Total Federal Participating Construction Cost: | $12,379,360.00 |
District: | District 2 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
|
|
|