MANSFIELD- CORRIDOR IMPROVEMENTS ON CHAUNCY STREET (ROUTE 106) FROM STATE ROUTE 140 TO COPELAND DRIVE
The purpose of this project is to improve traffic and safety for all users along Chauncy Street (Route 106) between and including the intersections of Route 140 and Copeland Drive (0.33 miles). Both the Route 106/Route 140 and Route 106/Copeland Street intersections are High Crash Clusters and will be reconstructed as part of the project. Specific improvements will be made to pedestrian and bicycle accommodations and safety along the corridor, while also rehabilitating the roadway pavement. Proposed improvements include pavement reconstruction by mill and overlay with areas of full depth box widening; sidewalk construction including a shared use path accommodating bicycles, and new signs and pavement markings. (This project is Phase 1 of 2, along the Route 106 corridor in Mansfield)
Location:
  • Town of Mansfield
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2025
    Project Manager: Gautam Sen
    Estimated Total Contract Cost: $8,725,382.50
    Estimated Total Federal Participating Construction Cost: $9,232,330.10
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: 75% Package Received (as of 01/30/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: MANSFIELD
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $1,403,357.40
    State Cost: $155,928.60
    Total Cost: $1,559,286.00

    Planned Federal FY: 2025
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: MANSFIELD
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $5,179,771.20
    State Cost: $1,294,942.80
    Total Cost: $6,474,714.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/27/2022
    Project Need Form PNF Approved 10/25/2022
    Project Initiation Form PIF Entered 10/27/2022
    Project Initiation Form PIF Approved 10/27/2022
    Project Initiation Form PRC Submitted 11/04/2022
    Project Review Committee PRC Approved 12/20/2022
    Project Management
    25% Design 25% Package Received 03/19/2021
    25% Design Design Public Hearing 03/02/2023
    75% Design 75% Package Received 01/30/2024