| Project Description: |
LENOX- INTERSECTION IMPROVEMENTS ON ROUTE 20 AT PLUNKETT STREET AND BLANTYRE ROAD
Project will implement intersection safety improvements (crash counter-measures) to be determined by FHWA/MassDOT RSA/ICE process. Improvements will likely consist of geometric changes (e.g. alignment changes on approaches, turning radii, etc.)
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Construction Begins: | Spring 2028 |
| Project Manager: | Anni H Autio![]() |
| Estimated Total Contract Cost: | $1,395,000.00 |
| Estimated Total Federal Participating Construction Cost: | $1,544,650.00 |
| Funding Provision: | This project is planned to be funded through the 2028 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization. |
| District: | District 1 |
| Current Status: | This project is in the preliminary design phase. |
|
Bridges |
||||||
|
|
||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||