Project Description:
LENOX- INTERSECTION IMPROVEMENTS ON ROUTE 20 AT PLUNKETT STREET AND BLANTYRE ROAD
Project will implement intersection safety improvements (crash counter-measures) to be determined by FHWA/MassDOT RSA/ICE process. Improvements will likely consist of geometric changes (e.g. alignment changes on approaches, turning radii, etc.)
Location:
  • Town of Lenox
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2027
    Project Manager: Anni H Autio
    Estimated Total Contract Cost: $1,395,000.00
    Estimated Total Federal Participating Construction Cost: $1,544,650.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: LENOX
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $1,557,007.20
    State Cost: $173,000.80
    Total Cost: $1,730,008.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/27/2022
    Project Need Form PNF Approved 10/27/2022
    Project Initiation Form PIF Entered 10/27/2022
    Project Initiation Form PIF Approved 10/27/2022
    Project Initiation Form PRC Submitted 11/23/2022
    Project Review Committee PRC Approved 12/20/2022
    Project Management