Project Description: |
REHOBOTH- BRIDGE REPLACEMENT, R-04-001, ROUTE 44 (WINTHROP STREET) OVER THE PALMER RIVER
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | Ryan P. Wilcox |
Estimated Total Contract Cost: | $2,646,600.00 |
Estimated Total Federal Participating Construction Cost: | $2,887,200.00 |
District: | District 5 |
Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 12/08/2024 ) |
|