| Project Description: |
TAUNTON- DRIVE INSTALLATION AND TRAFFIC SIGNAL UPDGRADES AT ROUTE 140 (COUNTY STREET) AND MOZZONE BOULEVARD
The purpose of this project is to relocate drive access to the MassDOT District 5 Office and to provide future access for the Bristol-Plymouth Regional Vocational High School. Work will include construction of a new drive and the addition of a fourth leg to the Route 140/Mozzone Boulevard intersection, including traffic signal upgrades.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Project Manager: | Aidee Cira![]() |
| Estimated Total Contract Cost: | $2,155,000.00 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 5 |
| Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 09/25/2024 ) |
|
Bridges |
||||||
|
|
|
|||||||||||||||||||||||||||||