Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
MALDEN- SPOT POND BROOK GREENWAY
Location:
  • City of Malden
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2028
    Project Manager: Adetoyin Ayoola Olaoye
    Estimated Total Contract Cost: $4,046,250.00
    Estimated Total Federal Participating Construction Cost: $4,337,612.50
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: MALDEN
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $4,858,127 (CMAQ, TAP)
  • Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $1,486,501.60
    State Cost: $371,625.40
    Total Cost: $1,858,127.00

    Planned Federal FY: 2027
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: MALDEN
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $4,858,127 (CMAQ, TAP)
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $2,400,000.00
    State Cost: $600,000.00
    Total Cost: $3,000,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/10/2022
    Project Need Form PNF Approved 11/04/2022
    Project Initiation Form PIF Entered 11/10/2022
    Project Initiation Form PIF Approved 11/10/2022
    Project Initiation Form PRC Submitted 11/28/2022
    Project Review Committee PRC Approved 12/20/2022
    Project Management