| Project Description: |
AUBURN- DECK REPLACEMENT, A-17-036 (1QN, 1QP), I-290 (EB/WB) OVER STATE ROUTE 12 (SOUTHBRIDGE STREET)
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Project Manager: | Alolade O Campbell![]() |
| Estimated Total Contract Cost: | $16,549,187.50 |
| Estimated Total Federal Participating Construction Cost: | $16,915,710.00 |
| District: | District 3 |
| Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 01/15/2025 ) |
|
Bridges
|
||||||
|
|
|
|||||||||||||||||||||||||||||