Project Description:
REHOBOTH- DECK REPLACEMENT, R-04-018 (3U4, 3U5), I-195 (EB/WB) OVER PALMER RIVER
The project involves removal of the existing non-composite bridge deck and replacement with a new 8” thick reinforced concrete composite bridge deck. The existing bridge railings will be replaced with new CF-MTL5 reinforced concrete bridge barriers. The width of the proposed bridge deck is 57’-2” with a roadway width of 53’-7 ½”. This project also involves the following. Replacement of all existing steel bridge bearings with proposed elastomeric bearings. Inspection of top cover plate end weld for fatigue cracks and repairs as required based on the inspections. Installation of steel bearing stiffeners at the east abutments only. Installation of new steel diaphragms in each bay offset 5’-0” from the centerline of each pier. Installation of new steel diaphragms in the stage construction bay. Modification of east backwall to support new bridge joint. Concrete repairs to bridge abutments, backwalls and pier. Work in the approach roadways shall include full depth reconstruction, bridge barrier to highway guardrail transitions, and highway guardrail. The demolition/construction will be conducted with staged construction so that two lanes of traffic are being maintained at all times.
Location:
  • Town of Rehoboth
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Ryan P. Wilcox
    Estimated Total Contract Cost: $10,201,636.46
    Estimated Total Federal Participating Construction Cost: $10,497,706.67
    District: District 5
    Current Status: 75% Package Comments to DE (as of 12/05/2025 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/21/2022
    Project Need Form PNF Approved 11/18/2022
    Project Initiation Form PIF Entered 11/21/2022
    Project Initiation Form PIF Approved 11/18/2022
    Project Initiation Form PRC Submitted 11/22/2022
    Project Review Committee PRC Approved 12/20/2022
    Project Management
    25% Design 25% Package Received 01/17/2025
    75% Design 75% Package Received 10/29/2025
    75% Design 75% Package Comments to DE 12/05/2025
    Consultant Contract Process NTP Issued 09/12/2023