Project Description:
QUINCY- SUPERSTRUCTURE REPLACEMENT, Q-01-038 (3FG), STEDMAN STREET OVER I-93/US-1/STATE ROUTE 3
The existing bridge is a 68'-11 5/8" two-span continuous structure comprised of steel rolled beams with an 8" composite deck, a reinforced concrete wall pier, and concrete gravity wall abutments and wingwalls. The proposed new bridge is anticipated to have the same overall plan geometry. Anticipated changes to the bridge geometry are higher vertical clearance, potential for wider sidewalks and new bicycle infrastructure, and potential of shallower structure depth to achieve higher clearance.
Location:
  • City of Quincy
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2029
    Project Manager: William F Brown
    Estimated Total Contract Cost: $2,319,068.57
    Estimated Total Federal Participating Construction Cost: $2,490,851.43
    Funding Provision: This project is planned to be funded through the 2029 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: The Contract Scope of Work has been sent to the Design Engineer for consideration (as of 04/23/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2029
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: QUINCY
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $2,311,509.60
    State Cost: $577,877.40
    Total Cost: $2,889,387.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/21/2022
    Project Need Form PNF Approved 11/18/2022
    Project Initiation Form PIF Entered 11/21/2022
    Project Initiation Form PIF Approved 11/18/2022
    Project Initiation Form PRC Submitted 11/22/2022
    Project Review Committee PRC Approved 12/20/2022
    Project Management
    Consultant Contract Process Scope to DE 04/23/2024