Project Description:
LITTLETON- DECK REPLACEMENT, L-13-030 (26V), STATE ROUTE 119 (GREAT ROAD) OVER I-495
This is primarily a deck replacement project. The proposed scope aims to replace the reinforced concrete deck with a new reinforced concrete deck.
Location:
  • Town of Littleton
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Herrio Lamothe
    Estimated Total Contract Cost: $12,616,885.88
    Estimated Total Federal Participating Construction Cost: $13,393,048.50
    District: District 3
    Current Status: 25% Package Comments to DE (as of 01/17/2025 )

    Contracts (1) Progress
    # 115791 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/21/2022
    Project Need Form PNF Approved 11/17/2022
    Project Initiation Form PIF Entered 11/21/2022
    Project Initiation Form PIF Approved 11/18/2022
    Project Initiation Form PRC Submitted 11/22/2022
    Project Review Committee PRC Approved 12/20/2022
    Project Management
    25% Design 25% Package Received 12/13/2024
    25% Design 25% Package Comments to DE 01/17/2025