| Planned Federal FY: |
2029 |
| Responsible MPO: |
Pioneer Valley Metropolitan Planning Organization |
| Location: |
Municipality |
| Cities: |
LUDLOW SPRINGFIELD
|
| Category: |
Advertised Projects Constr. |
| Budget Section: |
2A |
| Advance Construct: |
No |
| Air Quality Exempt: |
No |
No comments for this TIP line
|
|
| Category |
FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge |
|
| Federal Cost: |
$16,836,754.40 |
| State Cost: |
$4,209,188.60 |
| Total Cost: |
$21,045,943.00 |
|
|
|
| Planned Federal FY: |
2030 |
| Responsible MPO: |
Pioneer Valley Metropolitan Planning Organization |
| Location: |
Municipality |
| Cities: |
LUDLOW SPRINGFIELD
|
| Category: |
Advertised Projects Constr. |
| Budget Section: |
2A |
| Advance Construct: |
No |
| Air Quality Exempt: |
No |
No comments for this TIP line
|
|
| Category |
FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge |
|
| Federal Cost: |
$16,000,000.00 |
| State Cost: |
$4,000,000.00 |
| Total Cost: |
$20,000,000.00 |
|
|
|
| Planned Federal FY: |
2031 |
| Responsible MPO: |
Pioneer Valley Metropolitan Planning Organization |
| Location: |
Municipality |
| Cities: |
LUDLOW SPRINGFIELD
|
| Category: |
Advertised Projects Constr. |
| Budget Section: |
2A |
| Advance Construct: |
No |
| Air Quality Exempt: |
No |
No comments for this TIP line
|
|
| Category |
FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge |
|
| Federal Cost: |
$15,163,245.60 |
| State Cost: |
$3,790,811.40 |
| Total Cost: |
$18,954,057.00 |
|
|
|
|