Project Description:
TEWKSBURY- BRIDGE REPLACEMENT, T-03-013, NORTH STREET OVER I-495
Location:
  • Town of Tewksbury
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2028/2029
    Project Manager: Jacob Tanoglu
    Estimated Total Contract Cost: $31,266,400.00
    Estimated Total Federal Participating Construction Cost: $32,687,600.00
    Funding Provision: This project is planned to be funded through the 2029 Transportation Improvement Program for the Northern Middlesex Metropolitan Planning Organization.
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (1) Progress
    # 115795 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2029
    Responsible MPO: Northern Middlesex Metropolitan Planning Organization
    Location: Municipality
    Cities: TEWKSBURY
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge
    Federal Cost: $23,260,822.40
    State Cost: $5,815,205.60
    Total Cost: $29,076,028.00

    Planned Federal FY: 2030
    Responsible MPO: Northern Middlesex Metropolitan Planning Organization
    Location: Municipality
    Cities: TEWKSBURY
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge
    Federal Cost: $6,027,267.20
    State Cost: $1,506,816.80
    Total Cost: $7,534,084.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/25/2022
    Project Need Form PNF Approved 11/25/2022
    Project Initiation Form PIF Entered 11/25/2022
    Project Initiation Form PIF Approved 11/25/2022
    Project Initiation Form PRC Submitted 12/07/2022
    Project Review Committee PRC Approved 12/20/2022
    Project Management