Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
EVERETT- TARGETED MULTI-MODAL AND SAFETY IMPROVEMENTS ON ROUTE 16 (DESIGN ONLY)
The project team is proposing a two-phase approach for implementing infrastructure improvements along the project corridor. The first phase would include the implementation of short-term and mid-term safety enhancements recommended as part of the Road Safety Audit (RSA) that was conducted for the project corridor in August 2021, including reducing the roadway cross section from six lanes (three lanes in each direction) to four lanes (two lanes in each direction) to reduce vehicle conflict points and to provide safe facilities for pedestrians and cyclists along the corridor. These improvements would be implemented as a short-term targeted safety project using signs, pavement markings, minor traffic signal improvements, and limited ADA upgrades to assess operational and safety effects prior to a full corridor reconstruction project
Location:
  • City of Everett
  • Design Responsibility: Consultant
    Construction Begins: Autumn 2027
    Project Manager: Jacob Tanoglu
    Estimated Total Contract Cost: $4,375,000.00
    Estimated Total Federal Participating Construction Cost: $4,684,750.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: EVERETT
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Funded by BRMPO in 2027 as part of FFY2024-28 TIP. Project was not scored. Funded in full by HSIP.
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $4,722,228.00
    State Cost: $524,692.00
    Total Cost: $5,246,920.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/28/2022
    Project Need Form PNF Approved 11/21/2022
    Project Initiation Form PIF Entered 11/28/2022
    Project Initiation Form PIF Approved 11/28/2022
    Project Initiation Form PRC Submitted 12/09/2022
    Project Review Committee PRC Approved 12/20/2022
    Project Management