Project Description: |
BOSTON- DECK/SUPERSTRUCTURE REPLACEMENT, B-16-054 (4T2), BEACON STREET OVER I-90 (STRUCTURE 50, MILE 132.2)
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Autumn 2028 |
Project Manager: | William Henry Conroy![]() |
Estimated Total Contract Cost: | $34,876,435.00 |
Estimated Total Federal Participating Construction Cost: | $36,461,727.50 |
District: | District 6 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
|
|
|