Project Description:
NANTUCKET- INTERSECTION IMPROVEMENTS AT MILESTONE ROAD AND POLPIS ROAD AND EXTENSION OF 'SCONSET BIKEPATH
The purpose of this project is to improve intersection operations and safety at Milestone Road at Polpis Road in Nantucket, MA, through the design and construction of a new intersection configuration. The project will also include the construction of a shared-use-path on the north side of Milestone Road between Monomoy Road and the existing Polpis Bike Path for a distance of approximately 1600 feet. The project will make geometric changes to the Polpis Road approach to improve safety and accessibility for all users while providing an extension of the shared use path through the intersection on the north side of Milestone Road.
Location:
  • Town of Nantucket
  • Construction Begins: Autumn 2024
    Resident Engineer: Michael King
    Construction Bid Price: $5,774,502.50
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Nantucket Planning and Economic Development Commission.
    District: District 5
    Current Status: Currently constructing shared use path (placing HMA binder course) in addition to full depth reconstruction of roadway subject to roadway widening areas. Expect lane shifts and / or alternating traffic one-way traffic controlled by Police Details and/or Roadway Flaggers.. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. (as of 05/04/2025)

    Contracts (1) Progress
    # 126584 -- Construction Contract
    Intersection Improvements at Milestone Road and Polpis Road and Extension of 'Sconset Bikepath

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/24/2024
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Currently constructing shared use path (placing HMA binder course) in addition to full depth reconstruction of roadway subject to roadway widening areas. Expect lane shifts and / or alternating traffic one-way traffic controlled by Police Details and/or Roadway Flaggers.. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM.
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Nantucket Planning and Economic Development Commission
    Location: Municipality
    Cities: NANTUCKET
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm - Vulnerable User Safety / VUS
    Federal Cost: $591,817.50
    State Cost: $65,757.50
    Total Cost: $657,575.00

    Planned Federal FY: 2025
    Responsible MPO: Nantucket Planning and Economic Development Commission
    Location: Municipality
    Cities: NANTUCKET
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm - Vulnerable User Safety / VUS
    Federal Cost: $985,271.40
    State Cost: $109,474.60
    Total Cost: $1,094,746.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/07/2022
    Project Need Form PNF Approved 11/25/2022
    Project Initiation Form PIF Entered 12/07/2022
    Project Initiation Form PIF Approved 12/07/2022
    Project Initiation Form PRC Submitted 12/08/2022
    Project Review Committee PRC Approved 12/20/2022
    Project Status Advertised 06/29/2024
    Project Management
    100% Design 100% Package Received 02/20/2024
    100% Design 100% Package Comments to DE 03/25/2024
    25% Design 25% Package Received 06/01/2023
    75% Design 75% Package Received 06/01/2023
    75% Design 75% Package Comments to DE 07/10/2023
    Final Design PS&E Received 05/03/2024
    Final Design PS&E to FAPRO 06/07/2024
    Consultant Contract Process NTP Issued 03/07/2023