Project Description:
NANTUCKET- INTERSECTION IMPROVEMENTS AT MILESTONE ROAD AND POLPIS ROAD AND EXTENSION OF 'SCONSET BIKEPATH
The purpose of this project is to improve intersection operations and safety at Milestone Road at Polpis Road in Nantucket, MA, through the design and construction of a new intersection configuration. The project will also include the construction of a shared-use-path on the north side of Milestone Road between Monomoy Road and the existing Polpis Bike Path for a distance of approximately 1600 feet. The project will make geometric changes to the Polpis Road approach to improve safety and accessibility for all users while providing an extension of the shared use path through the intersection on the north side of Milestone Road.
Location:
  • Town of Nantucket
  • Design Responsibility: Consultant
    Construction Begins: Autumn 2024
    Project Manager: Adam W Kiel
    Estimated Total Contract Cost: $2,637,495.10
    Estimated Total Federal Participating Construction Cost: $2,952,320.91
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Nantucket Planning and Economic Development Commission.
    District: District 5
    Current Status: 100% Package Comments to DE (as of 03/25/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Nantucket Planning and Economic Development Commission
    Location: Municipality
    Cities: NANTUCKET
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • GHG analysis to be conducted when design status is at 75%.
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $602,045.10
    State Cost: $66,893.90
    Total Cost: $668,939.00

    Planned Federal FY: 2024
    Responsible MPO: Nantucket Planning and Economic Development Commission
    Location: Municipality
    Cities: NANTUCKET
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • GHG analysis to be conducted when design status is at 75%.
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $477,954.90
    State Cost: $53,106.10
    Total Cost: $531,061.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/07/2022
    Project Need Form PNF Approved 11/25/2022
    Project Initiation Form PIF Entered 12/07/2022
    Project Initiation Form PIF Approved 12/07/2022
    Project Initiation Form PRC Submitted 12/08/2022
    Project Review Committee PRC Approved 12/20/2022
    Project Management
    100% Design 100% Package Received 02/20/2024
    100% Design 100% Package Comments to DE 03/25/2024
    25% Design 25% Package Received 06/01/2023
    75% Design 75% Package Received 06/01/2023
    75% Design 75% Package Comments to DE 07/10/2023
    Consultant Contract Process NTP Issued 03/07/2023