Project Description: |
BOSTON- BRIDGE REPLACEMENT, B-16-033, MORRSSEY BOULEVARD OVER DORCHESTER BAY
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | Joseph Breen![]() |
Estimated Total Contract Cost: | $122,499,960.00 |
Estimated Total Federal Participating Construction Cost: | $128,068,140.00 |
District: | District 6 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges |
|
|
|