Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WEST BRIDGEWATER- BRIDGE REPLACEMENT, W-18-004, FOREST STREET OVER TOWN RIVER
Location:
  • Town of West Bridgewater
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Project Manager: Anni H Autio
    Estimated Total Contract Cost: $4,015,825.00
    Estimated Total Federal Participating Construction Cost: $4,380,900.00
    District: District 5
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 06/21/2023 )

    Contracts (1) Progress
    # 115744 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/08/2022
    Project Need Form PNF Approved 12/08/2022
    Project Initiation Form PIF Entered 12/08/2022
    Project Initiation Form PIF Approved 12/08/2022
    Project Initiation Form PRC Submitted 12/08/2022
    Project Review Committee PRC Approved 12/20/2022
    Project Management
    Consultant Contract Process Scope to DE 04/28/2023
    Consultant Contract Process NTP Issued 06/21/2023