| Project Description: |
CHICOPEE- SUPERSTRUCTURE REPLACEMENT OF C-13-003, ROUTE 116 OVER BMRR
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Construction Begins: | Summer 2029 |
| Project Manager: | Aleksey N Belov![]() |
| Estimated Total Contract Cost: | $17,759,390.00 |
| Estimated Total Federal Participating Construction Cost: | $18,566,635.00 |
| Funding Provision: | This project is planned to be funded through the 2029 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization. |
| District: | District 2 |
| Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 08/23/2023 ) |
|