Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WASHINGTON- BRIDGE REPLACEMENT, W-09-012, LOWER VALLEY RD OVER DEPOT BROOK
Location:
  • Town of Washington
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2028
    Project Manager: Stephen Soma
    Estimated Total Contract Cost: $2,365,550.00
    Estimated Total Federal Participating Construction Cost: $2,580,600.00
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: WASHINGTON
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Bridge Formula Program - Local Off System Bridge
    Federal Cost: $2,993,496.00
    State Cost: $0.00
    Total Cost: $2,993,496.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/11/2022
    Project Need Form PNF Approved 12/11/2022
    Project Initiation Form PIF Entered 12/11/2022
    Project Initiation Form PIF Approved 12/11/2022
    Project Initiation Form PRC Submitted 12/11/2022
    Project Review Committee PRC Approved 12/20/2022
    Project Management