Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
ATHOL- ORANGE- BRIDGE REPLACEMENT, A-15-017=O-03-001, LOGAN ROAD OVER THE EAST BRANCH OF THE TULLY RIVER
Location:
  • Town of Athol
  • Town of Orange
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2028
    Project Manager: Anni H Autio
    Estimated Total Contract Cost: $3,077,000.00
    Estimated Total Federal Participating Construction Cost: $3,298,046.25
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the STATEWIDE.
    District: District 2
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: STATEWIDE
    Location: Municipality
    Cities: ATHOL
    ORANGE
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Bridge Formula Program - Local Off System Bridge
    Federal Cost: $3,693,812.00
    State Cost: $0.00
    Total Cost: $3,693,812.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/15/2022
    Project Need Form PNF Approved 12/15/2022
    Project Initiation Form PIF Entered 12/15/2022
    Project Initiation Form PIF Approved 12/15/2022
    Project Initiation Form PRC Submitted 12/15/2022
    Project Review Committee PRC Approved 12/20/2022
    Project Management