Project Description:
BERNARDSTON- LEDGE REMOVAL FOR HIGHWAY SAFETY AT VARIOUS LOCATION
The scope of the project includes the removal of potentially hazardous ledge from the northbound side of the freeway. Safe and effective removal of the ledge will prevent it from falling on a vehicle without warning.
Location:
  • Town of Bernardston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2027
    Project Manager: Jonathan E Freeman
    Estimated Total Contract Cost: $1,915,643.18
    Estimated Total Federal Participating Construction Cost: $1,961,274.22
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Franklin Regional Council of Governments.
    District: District 2
    Current Status: 75% Package Received (as of 06/05/2026 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Franklin Regional Council of Governments
    Location: Municipality
    Cities: BERNARDSTON
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Moved $208,173.00 to HPP per STIP Action 1
  • Category FA - Promoting Resilient Operations for Transformative, Efficient, and Cost-saving Transportation (PROTECT)
    Federal Cost: $1,713,264.00
    State Cost: $428,316.00
    Total Cost: $2,141,580.00
    Category FA - High Priority Projects (HPP)
    Federal Cost: $166,538.40
    State Cost: $41,634.60
    Total Cost: $208,173.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/19/2022
    Project Need Form PNF Approved 12/19/2022
    Project Initiation Form PIF Entered 12/19/2022
    Project Initiation Form PIF Approved 12/19/2022
    Project Initiation Form PRC Submitted 04/19/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Management
    25% Design 25% Package Received 06/05/2026
    75% Design 75% Package Received 06/05/2026