| Project Description: |
BERNARDSTON- LEDGE REMOVAL FOR HIGHWAY SAFETY AT VARIOUS LOCATION
The scope of the project includes the removal of potentially hazardous ledge from the northbound side of the freeway. Safe and effective removal of the ledge will prevent it from falling on a vehicle without warning.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Construction Begins: | Spring 2027 |
| Project Manager: | Jonathan E Freeman![]() |
| Estimated Total Contract Cost: | $1,915,643.18 |
| Estimated Total Federal Participating Construction Cost: | $1,961,274.22 |
| Funding Provision: | This project is planned to be funded through the 2027 Transportation Improvement Program for the Franklin Regional Council of Governments. |
| District: | District 2 |
| Current Status: | 75% Package Comments to DE (as of 07/14/2026 ) |
|
Bridges |
||||||
|
|
||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||