Project Description:
BARNSTABLE- CULVERT REPLACEMENT ON ROUTE 6A OVER BOAT COVE CREEK
Location:
  • Town of Barnstable
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2028
    Project Manager: Joseph Gyujong Yoo
    Estimated Total Contract Cost: $996,000.00
    Estimated Total Federal Participating Construction Cost: $1,208,980.00
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Cape Cod Metropolitan Planning Organization.
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Cape Cod Metropolitan Planning Organization
    Location: Municipality
    Cities: BARNSTABLE
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • TFPC - $1,354,058
  • Category FA - Promoting Resilient Operations for Transformative, Efficient, and Cost-saving Transportation (PROTECT)
    Federal Cost: $1,083,246.40
    State Cost: $270,811.60
    Total Cost: $1,354,058.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/23/2022
    Project Need Form PNF Approved 12/20/2022
    Project Initiation Form PIF Entered 12/23/2022
    Project Initiation Form PIF Approved 12/23/2022
    Project Initiation Form PRC Submitted 04/06/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Management