STOCKBRIDGE- CULVERT REPLACEMENT ON ROUTE 7 OVER KAMPOOSA BROOK
Location:
  • Town of Stockbridge
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2028
    Project Manager: Jonathan E Freeman
    Estimated Total Contract Cost: $2,810,000.00
    Estimated Total Federal Participating Construction Cost: $2,889,300.00
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: STOCKBRIDGE
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Promoting Resilient Operations for Transformative, Efficient, and Cost-saving Transportation (PROTECT)
    Federal Cost: $2,588,812.80
    State Cost: $647,203.20
    Total Cost: $3,236,016.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/05/2023
    Project Need Form PNF Approved 01/04/2023
    Project Initiation Form PIF Entered 01/05/2023
    Project Initiation Form PIF Approved 01/04/2023
    Project Initiation Form PRC Submitted 02/09/2023
    Project Review Committee PRC Approved 03/06/2023