Project Description:
LYNNFIELD- PEABODY- RAIL TRAIL CONSTRUCTION, FROM FORD AVENUE TO NICHOLS LANE (PHASE 1)
Phase 1 consists of about 1.8 miles of shared-use path, extending from Ford Avenue in Lynnfield to Nichols Lane in Peabody with two roadway crossings at Summer Street and Pillings Pond Road. The path is 12 feet wide with 2-foot-wide grass shoulders constructed mostly on the former railroad track bed. The project scope also includes minor landscaping, trail amenities (benches, interpretive signage, bicycle racks, etc.), wetland replication, removal of former railroad structures, ADA compliant pedestrian curb ramps at crossings, a pedestrian activated warning beacon, traffic signage, and pavement markings.
Location:
  • Town of Lynnfield
  • City of Peabody
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2028/2029
    Project Manager: Shahpar Negah
    Estimated Total Contract Cost: $5,352,662.00
    Estimated Total Federal Participating Construction Cost: $5,829,514.00
    Funding Provision: This project is planned to be funded through the 2029 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: 100% Package Received (as of 02/07/2025 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2029
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: LYNNFIELD
    Category: Advertised Projects Constr.
    Budget Section: 2C
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $8,000,000.00
    State Cost: $2,000,000.00
    Total Cost: $10,000,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/18/2023
    Project Need Form PNF Approved 10/27/2022
    Project Initiation Form PIF Entered 01/18/2023
    Project Initiation Form PIF Approved 11/28/2022
    Project Initiation Form PRC Submitted 05/22/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Management
    100% Design 100% Package Received 02/07/2025
    75% Design 75% Package Received 07/16/2024
    75% Design 75% Package Comments to DE 10/22/2024
    Consultant Contract Process NTP Issued 01/17/2023