Project Description:
ATHOL- PHILLIPSTON- TEMPLETON- BRIDGE PRESERVATION OF 8 BRIDGE CROSSINGS ALONG ROUTE 2
Bridge preservation including in kind repairs of 8 bridges along Route 2. Work will include substructure, superstructure, deck and joint work.
Location:
  • Town of Athol
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2024
    Project Manager: Albin Napit
    Estimated Total Contract Cost: $15,445,980.40
    Estimated Total Federal Participating Construction Cost: $15,861,265.85
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Montachusett Metropolitan Planning Organization.
    District: District 2
    Current Status: This project has been advertised for construction bids. (as of 12/30/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Montachusett Metropolitan Planning Organization
    Location: Municipality
    Cities: ATHOL
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • HIP-BR
  • HIP/BR increased from 9,499,000.00 to $11,186,059 and BR/OFFS added via STIP Action #1.
  • Category FA - Bridge Formula Program - State Off System Bridge
    Federal Cost: $3,202,576.80
    State Cost: $800,644.20
    Total Cost: $4,003,221.00
    Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $8,948,847.20
    State Cost: $2,237,211.80
    Total Cost: $11,186,059.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/24/2023
    Project Need Form PNF Approved 01/09/2023
    Project Initiation Form PIF Entered 01/24/2023
    Project Initiation Form PIF Approved 01/20/2023
    Project Initiation Form PRC Submitted 02/27/2023
    Project Review Committee PRC Approved 03/01/2023
    Project Status Advertised 12/30/2023
    Project Management
    100% Design 100% Package Received 11/08/2023
    100% Design 100% Package Comments to DE 11/28/2023
    75% Design 75% Package Received 09/07/2023
    75% Design 75% Package Comments to DE 10/19/2023
    Final Design PS&E Received 12/06/2023
    Final Design PS&E Received - Resub 1 12/18/2023