Project Description:
DISTRICT 5- SCHEDULED AND EMERGENCY STEEL AND CONCRETE BEAM REPAIRS AT VARIOUS LOCATIONS
The work under this Project consists of scheduled and emergency steel and concrete beam repairs on bridges throughout District 5.
Location:
Construction Begins: Winter 2023/2024
Resident Engineer: Michael Horton
Construction Bid Price: $1,993,386.00
District: District 5
Current Status: - MIG is scheduling work at a few work order locations to begin on 4/12/26: WO #6 – Hingham WO #5 – Foxboro WO #4 – Wrentham Normal work hours are Monday through Friday, 9:00 PM to 5:30 AM Expect periodic lane closures and restrictions. (as of 03/30/2026)
Additional Info: WO #1 - Pleasant St. over RT-24, Brockton - Traffic control install complete 4/27/24. No other field work completed. (as of 03/30/2026)

Contracts (1) Progress
# 124461 -- Construction Contract
Scheduled and Emergency Steel and Concrete Beam Repairs at Various Locations 32% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/26/2023
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    - MIG is scheduling work at a few work order locations to begin on 4/12/26: WO #6 – Hingham WO #5 – Foxboro WO #4 – Wrentham Normal work hours are Monday through Friday, 9:00 PM to 5:30 AM Expect periodic lane closures and restrictions.
    Additional Info
    WO #1 - Pleasant St. over RT-24, Brockton - Traffic control install complete 4/27/24. No other field work completed.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/26/2023
    Project Need Form PNF Approved 01/26/2023
    Project Initiation Form PIF Entered 01/26/2023
    Project Initiation Form PIF Approved 01/26/2023
    Project Initiation Form PRC Submitted 01/27/2023
    Project Review Committee PRC Approved 01/30/2023
    Project Status Advertised 10/28/2023
    Project Management
    100% Design 100% Package Received 07/07/2023
    100% Design 100% Package Comments to DE 09/14/2023
    Final Design PS&E Received 09/29/2023
    Final Design PS&E to FAPRO 10/23/2023