| Project Description: |
DISTRICT 5- SCHEDULED AND EMERGENCY STEEL AND CONCRETE BEAM REPAIRS AT VARIOUS LOCATIONS
The work under this Project consists of scheduled and emergency steel and concrete beam repairs on bridges throughout District 5.
|
| Location: | |
| Construction Begins: | Winter 2023/2024 |
| Resident Engineer: | Michael Horton![]() |
| Construction Bid Price: | $1,993,386.00 |
| District: | District 5 |
| Current Status: | - MIG is scheduling work at a few work order locations to begin on 4/12/26: WO #6 – Hingham WO #5 – Foxboro WO #4 – Wrentham Normal work hours are Monday through Friday, 9:00 PM to 5:30 AM Expect periodic lane closures and restrictions. (as of 03/30/2026) |
| Additional Info: | WO #1 - Pleasant St. over RT-24, Brockton - Traffic control install complete 4/27/24. No other field work completed. (as of 03/30/2026) |
|
Bridges |
||||||||
|
||||||||||
|
|
|
|||||||||||||||||||||||||||||||||||||||||