DISTRICT 5- SCHEDULED AND EMERGENCY STEEL AND CONCRETE BEAM REPAIRS AT VARIOUS LOCATIONS
The work under this Project consists of scheduled and emergency steel and concrete beam repairs on bridges throughout District 5.
Location:
Construction Begins: Winter 2023/2024
Resident Engineer: Scott Borges
Construction Bid Price: $1,993,386.00
District: District 5
Current Status: Field office mobilization only. Lease start date 4/15/24. Work order start date TBD. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. (as of 05/02/2024)

Contracts (1) Progress
# 124461 -- Construction Contract
Scheduled and Emergency Steel and Concrete Beam Repairs at Various Locations 1% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/26/2023
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Field office mobilization only. Lease start date 4/15/24. Work order start date TBD. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/26/2023
    Project Need Form PNF Approved 01/26/2023
    Project Initiation Form PIF Entered 01/26/2023
    Project Initiation Form PIF Approved 01/26/2023
    Project Initiation Form PRC Submitted 01/27/2023
    Project Review Committee PRC Approved 01/30/2023
    Project Status Advertised 10/28/2023
    Project Management
    100% Design 100% Package Received 07/07/2023
    100% Design 100% Package Comments to DE 09/14/2023
    Final Design PS&E Received 09/29/2023
    Final Design PS&E to FAPRO 10/23/2023