Project Description: |
FALL RIVER- EXPANDED METAL SHIELDING INSTALLATION ON F-02-058 (3TK), I-195 (EB/WB) OVER TAUNTON RIVER
|
Location: |
|
Construction Begins: | Autumn 2023 |
Resident Engineer: | Nuno Redondo![]() |
Construction Bid Price: | $593,086.02 |
District: | District 5 |
Current Status: | Contractors installing shielding under bridge. Scheduled work hours are Monday through Friday, 8:30 PM to 5:00 PM. Expect periodic lane closures and restrictions. (as of 03/24/2025) |
|
Bridges
|
|
|
|
|