Project Description:
NORTHBOROUGH- BRIDGE PRESERVATION, N-20-025 (1R8, 1R9), I-290 OVER MDC AQUEDUCT AND CSX RAILROAD
Bridge preservation including structural steel repairs and painting at I-290 over the MDC Aqueduct and CSX Railroad.
Location:
  • Town of Northborough
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2024
    Project Manager: Genesis Poz Diaz
    Estimated Total Federal Participating Construction Cost: $2,400,000.00
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: 75% Package Received (as of 04/08/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: NORTHBOROUGH
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $2,400,000, Design Status = Approved
  • Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $1,920,000.00
    State Cost: $480,000.00
    Total Cost: $2,400,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/27/2023
    Project Need Form PNF Approved 01/27/2023
    Project Initiation Form PIF Entered 01/27/2023
    Project Initiation Form PIF Approved 01/27/2023
    Project Initiation Form PRC Submitted 02/27/2023
    Project Review Committee PRC Approved 03/01/2023
    Project Management
    75% Design 75% Package Received 04/08/2024