Project Description:
BOSTON- NEWTON- BRIDGE PRESERVATION OF 3 BRIDGES ALONG STATE ROUTE 9/BOYLSTON STREET
This project will restore the masonry and upgrade the traffic safety system on three bridges carrying or over route 9 in the City of Boston and Town of Newton.
Location:
  • City of Boston
  • City of Newton
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2025
    Project Manager: Alyson Bedard
    Estimated Total Contract Cost: $9,086,000.00
    Estimated Total Federal Participating Construction Cost: $9,499,000.00
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BOSTON
    NEWTON
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $7,599,200.00
    State Cost: $1,899,800.00
    Total Cost: $9,499,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/27/2023
    Project Need Form PNF Approved 01/27/2023
    Project Initiation Form PIF Entered 01/27/2023
    Project Initiation Form PIF Approved 01/27/2023
    Project Initiation Form PRC Submitted 02/27/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Management