Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
HUNTINGTON- BRIDGE PRESERVATION, H-27-006 (0DH), STATE ROUTE 112/EAST MAIN STREET OVER CSXT AND WESTFIELD RIVER
This project consists of deck, superstructure, and substructure repairs in kind to restore bridges to state of good repair.
Location:
  • Town of Huntington
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2025
    Project Manager: Stephen Soma
    Estimated Total Contract Cost: $11,495,000.00
    Estimated Total Federal Participating Construction Cost: $12,017,500.00
    District: District 1
    Current Status: The Contract Scope of Work has been sent to the Design Engineer for consideration (as of 12/08/2023 )

    Contracts (1) Progress
    # 115745 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/30/2023
    Project Need Form PNF Approved 01/26/2023
    Project Initiation Form PIF Entered 01/30/2023
    Project Initiation Form PIF Approved 01/30/2023
    Project Initiation Form PRC Submitted 04/21/2023
    Project Review Committee PRC Approved 08/11/2023
    Project Management
    Consultant Contract Process Scope to DE 11/07/2023
    Consultant Contract Process Scope to DE 12/08/2023