Project Description:
HUNTINGTON- BRIDGE PRESERVATION, H-27-006 (0DH), STATE ROUTE 112/EAST MAIN STREET OVER CSXT AND WESTFIELD RIVER
This project consists of deck, superstructure, and substructure repairs in kind to restore bridges to state of good repair.
Location:
  • Town of Huntington
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2025
    Project Manager: Stephen Soma
    Estimated Total Contract Cost: $14,943,211.13
    Estimated Total Federal Participating Construction Cost: $15,397,137.00
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 1
    Current Status: 25% Package Received (as of 08/12/2024 )

    Contracts (1) Progress
    # 115745 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: HUNTINGTON
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $9,614,000.00
    State Cost: $2,403,500.00
    Total Cost: $12,017,500.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/30/2023
    Project Need Form PNF Approved 01/26/2023
    Project Initiation Form PIF Entered 01/30/2023
    Project Initiation Form PIF Approved 01/30/2023
    Project Initiation Form PRC Submitted 04/21/2023
    Project Review Committee PRC Approved 08/11/2023
    Project Management
    25% Design 25% Package Received 08/12/2024
    Consultant Contract Process Scope to DE 11/07/2023
    Consultant Contract Process Scope to DE 12/08/2023