Project Description:
WEST SPRINGFIELD- DECK REPLACEMENT, W-21-037 (110 & 10Y), I-91 OVER I-90 AND W-21-036 (13L), BRUSH HILL OVER I-91
This is primarily a deck replacement project which aims to replace the reinforced concrete deck with a new reinforced concrete deck. All three steel superstructures will be cleaned and painted. Concrete bridge piers and abutments will be repaired. Finally, the work also includes full-depth pavement construction, pavement milling and resurfacing, granite curbing, cement-concrete sidewalk and pedestrian curb ramps, drainage structure adjustments and cleaning, guardrail and transitions to bridge rail, removal and re-anchorage of cable guardrail, loam and seed, and all incidental work.
Location:
  • Town of West Springfield
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2027
    Project Manager: Lawrence Cash
    Estimated Total Contract Cost: $28,212,395.23
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 2
    Current Status: 75% Package Received (as of 10/13/2026 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/30/2023
    Project Need Form PNF Approved 01/24/2023
    Project Initiation Form PIF Entered 01/30/2023
    Project Initiation Form PIF Approved 01/30/2023
    Project Initiation Form PRC Submitted 04/21/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Management
    25% Design 25% Package Received 01/30/2026
    25% Design 25% Package Comments to DE 03/06/2026
    25% Design 25% Package Comments to DE 03/06/2026
    25% Design 25% Package Approved 08/21/2026
    75% Design 75% Package Received 10/13/2026
    Consultant Contract Process NTP Issued 12/11/2024