| Project Description:
|
WEST SPRINGFIELD- DECK REPLACEMENT, W-21-037 (110 & 10Y), I-91 OVER I-90 AND W-21-036 (13L), BRUSH HILL OVER I-91
This is primarily a deck replacement project which aims to replace the reinforced concrete deck with a new reinforced concrete deck. All three steel superstructures will be cleaned and painted. Concrete bridge piers and abutments will be repaired. Finally, the work also includes full-depth pavement construction, pavement milling and resurfacing, granite curbing, cement-concrete sidewalk and pedestrian curb ramps, drainage structure adjustments and cleaning, guardrail and transitions to bridge rail, removal and re-anchorage of
cable guardrail, loam and seed, and all incidental work.
|