Project Description:
WEST SPRINGFIELD- DECK REPLACEMENT, W-21-037 (110 & 10Y), I-91 OVER I-90 AND W-21-036 (13L), BRUSH HILL OVER I-91
The bridge deck replacement project is proposed to extend the life of the structure as part of an overall bridge preservation strategy. This is primarily a deck replacement project which aims to replace the reinforced concrete deck with a new reinforced concrete deck.
Location:
  • Town of West Springfield
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2027
    Project Manager: Lawrence Cash
    Estimated Total Contract Cost: $11,726,000.00
    Estimated Total Federal Participating Construction Cost: $12,259,000.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: WEST SPRINGFIELD
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $10,591,776.00
    State Cost: $2,647,944.00
    Total Cost: $13,239,720.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/30/2023
    Project Need Form PNF Approved 01/24/2023
    Project Initiation Form PIF Entered 01/30/2023
    Project Initiation Form PIF Approved 01/30/2023
    Project Initiation Form PRC Submitted 04/21/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Management