Project Description:
DARTMOUTH TO WAREHAM- GUIDE AND TRAFFIC SIGN REPLACEMENT ON A SECTION OF INTERSTATE 195
This project will replace and update existing guide and traffic signs, including support structures and posts, along Interstate 195 between Faunce Corner Road in Dartmouth and Interstate 495/Route 25 in Wareham.
Location:
  • Town of Dartmouth
  • Town of Fairhaven
  • Town of Marion
  • Town of Mattapoisett
  • City of New Bedford
  • Town of Wareham
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2024
    Project Manager: Stephen Timmins
    Estimated Total Contract Cost: $7,712,443.05
    Estimated Total Federal Participating Construction Cost: $7,979,196.83
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: This project has been advertised for construction bids. (as of 03/16/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: DARTMOUTH
    FAIRHAVEN
    MARION
    MATTAPOISETT
    NEW BEDFORD
    WAREHAM
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $6,902,325.00
    State Cost: $766,925.00
    Total Cost: $7,669,250.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/09/2023
    Project Initiation Form PIF Entered 02/09/2023
    Project Initiation Form PRC Submitted 02/09/2023
    Project Review Committee PRC Approved 02/14/2023
    Project Status Advertised 03/16/2024
    Project Management
    100% Design 100% Package Received 09/18/2023
    100% Design 100% Package Comments to DE 11/16/2023
    Final Design PS&E Received 09/18/2023
    Final Design PS&E to FAPRO 03/01/2024