Project Description:
WAREHAM TO RAYNHAM- GUIDE AND TRAFFIC SIGN REPLACEMENT ON A SECTION OF INTERSTATE 495
This project will replace and update the existing guide and traffic signs, including support structures and posts, along Interstate 495 between I-195/Route 25 in Wareham and Route 24 in Raynham, with new signs and supports/posts.
Location:
  • Town of Middleborough
  • Town of Raynham
  • Town of Wareham
  • Construction Begins: Summer 2024
    Resident Engineer: Matthew Blackwell
    Construction Bid Price: $4,423,951.40
    District: District 5
    Current Status: The contractor is installing foundations for new ground mounted signs. Scheduled work hours are Monday through Friday, 7:00 AM to 3:30 PM. (as of 11/05/2024)

    Contracts (1) Progress
    # 125648 -- Construction Contract
    Guide and Traffic Sign Replacement on a Section of Interstate 495 5% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/01/2024
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    The contractor is installing foundations for new ground mounted signs. Scheduled work hours are Monday through Friday, 7:00 AM to 3:30 PM.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/09/2023
    Project Initiation Form PIF Entered 02/09/2023
    Project Initiation Form PRC Submitted 02/09/2023
    Project Review Committee PRC Approved 02/14/2023
    Project Status Advertised 03/30/2024
    Project Management
    100% Design 100% Package Received 10/19/2023
    100% Design 100% Package Comments to DE 12/04/2023
    75% Design 75% Package Received 10/19/2023
    Final Design PS&E Received 01/16/2024
    Final Design PS&E to FAPRO 03/19/2024