Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BURLINGTON- LYNNFIELD- WAKEFIELD- WOBURN- BRIDGE PRESERVATION OF 10 BRIDGES CARRYING I-95
Bridge preservation of 10 reinforced concrete frame bridges in Burlington, Lynnfield, Wakefield, and Woburn to include concrete patching and railing upgrades.
Location:
  • Town of Burlington
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2025/2026
    Project Manager: Genesis Poz Diaz
    Estimated Total Contract Cost: $12,610,962.75
    Estimated Total Federal Participating Construction Cost: $12,948,242.88
    District: District 4
    Current Status: 75% Package Received - Resub 2 (as of 04/24/2024 )

    Contracts (1) Progress
    # 115773 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/13/2023
    Project Need Form PNF Approved 01/26/2023
    Project Initiation Form PIF Entered 02/13/2023
    Project Initiation Form PIF Approved 02/13/2023
    Project Initiation Form PRC Submitted 02/27/2023
    Project Review Committee PRC Approved 03/01/2023
    Project Management
    75% Design 75% Package Received 12/15/2023
    75% Design 75% Package Comments to DE 01/18/2024
    75% Design 75% Package Received - Resub 1 02/22/2024
    75% Design 75% Package Received - Resub 2 04/24/2024
    Consultant Contract Process NTP Issued 08/16/2023