Project Description:
BURLINGTON- LYNNFIELD- WAKEFIELD- WOBURN- BRIDGE PRESERVATION OF 10 BRIDGES CARRYING I-95
Bridge preservation of 10 reinforced concrete frame bridges in Burlington, Lynnfield, Wakefield, and Woburn to include concrete patching and railing upgrades.
Location:
  • Town of Burlington
  • Town of Lynnfield
  • Town of Wakefield
  • City of Woburn
  • Construction Begins: Spring 2026
    Resident Engineer: Austin Franklin
    Construction Bid Price: $11,671,740.00
    District: District 4

    Contracts (2) Progress
    # 115773 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 133292 -- Construction Contract
    Bridge Preservation of 10 Bridges carrying I-95

    Bridges

    Contract Dates
    Notice to Proceed: 04/13/2026
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/13/2023
    Project Need Form PNF Approved 01/26/2023
    Project Initiation Form PIF Entered 02/13/2023
    Project Initiation Form PIF Approved 02/13/2023
    Project Initiation Form PRC Submitted 02/27/2023
    Project Review Committee PRC Approved 03/01/2023
    Project Status Advertised 01/03/2026
    Project Management
    100% Design 100% Package Received 01/13/2025
    100% Design 100% Package Comments to DE 02/28/2025
    100% Design 100% Package Received - Resub 1 04/22/2025
    75% Design 75% Package Received 12/15/2023
    75% Design 75% Package Comments to DE 01/18/2024
    75% Design 75% Package Received - Resub 1 02/22/2024
    75% Design 75% Package Received - Resub 2 04/24/2024
    Final Design PS&E Received 07/03/2025
    Final Design PS&E Received - Resub 1 10/27/2025
    Final Design PS&E Received - Resub 2 12/17/2025
    Consultant Contract Process NTP Issued 08/16/2023