Project Description:
SOMERSET- BRIDGE PRESERVATION OF S-16-009 (3Y9), S-16-010 (3PD), S-16-011 (3YA) AND S-16-012 (3U6 & 3U7) ALONG I-195
Location:
  • Town of Somerset
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2024
    Project Manager: Albin Napit
    Estimated Total Contract Cost: $8,360,346.00
    Estimated Total Federal Participating Construction Cost: $8,585,149.00
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: 75% Package Received (as of 04/19/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: SOMERSET
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $6,400,000.00
    State Cost: $1,600,000.00
    Total Cost: $8,000,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/14/2023
    Project Need Form PNF Approved 02/14/2023
    Project Initiation Form PIF Entered 02/14/2023
    Project Initiation Form PIF Approved 02/14/2023
    Project Initiation Form PRC Submitted 02/15/2023
    Project Review Committee PRC Approved 03/01/2023
    Project Management
    75% Design 75% Package Received 04/19/2024