Project Description: |
CHARLEMONT- CHESHIRE- HUNTINGTON- BRIDGE PRESERVATION, C-05-024 (0KW), C-10-001 (0CU), C-10-010 (0CV), AND H-27-020 (0CN)
Work consists of deck, superstructure, and substructure repair on bridges carrying Rte 112 over the Westfield River, Rte 2 over the railroad west of Tower Road, and two bridges carrying Rte 116 over Dry Brook in the towns of Charlemont, Cheshire, and Huntington.
|
Location: |
|
Design Responsibility: | In-House Boston |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Summer 2028 |
Project Manager: | Alyson Bedard |
Estimated Total Contract Cost: | $5,778,000.00 |
Estimated Total Federal Participating Construction Cost: | $6,206,000.00 |
Funding Provision: | This project is planned to be funded through the 2028 Transportation Improvement Program for the STATEWIDE. |
District: | District 1 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
|
|
|