CHARLEMONT- CHESHIRE- HUNTINGTON- BRIDGE PRESERVATION, C-05-024 (0KW), C-10-001 (0CU), C-10-010 (0CV), AND H-27-020 (0CN)
Work consists of deck, superstructure, and substructure repair on bridges carrying Rte 112 over the Westfield River, Rte 2 over the railroad west of Tower Road, and two bridges carrying Rte 116 over Dry Brook in the towns of Charlemont, Cheshire, and Huntington.
Location:
  • Town of Charlemont
  • Town of Cheshire
  • Town of Huntington
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2028
    Project Manager: Alina Daragan
    Estimated Total Contract Cost: $6,334,840.00
    Estimated Total Federal Participating Construction Cost: $6,775,850.00
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the STATEWIDE.
    District: District 1
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: STATEWIDE
    Location: Municipality
    Cities: CHARLEMONT
    CHESHIRE
    HUNTINGTON
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $5,560,576.00
    State Cost: $1,390,144.00
    Total Cost: $6,950,720.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/23/2023
    Project Need Form PNF Approved 02/22/2023
    Project Initiation Form PIF Entered 02/23/2023
    Project Initiation Form PIF Approved 02/22/2023
    Project Initiation Form PRC Submitted 02/23/2023
    Project Review Committee PRC Approved 06/01/2023