Project Description:
WORCESTER- BRIDGE PRESERVATION OF 11 STRUCTURES ON I-190 AND RAMPS
Work consists of cleaning & painting of structural steel on bridges W-44-124 (1XF, 1XG), W-44-126 (1XJ, 1XK), W-44-127 (1XL), W-44-132 (1XN, 1XP), and W-44-133 (1XQ, 1XR) in the town of Worcester.
Location:
  • City of Worcester
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2025
    Project Manager: Genesis Poz Diaz
    Estimated Total Contract Cost: $15,261,849.13
    Estimated Total Federal Participating Construction Cost: $15,768,663.38
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: WORCESTER
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $7,500,000, Design Status = Approved
  • Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $6,000,000.00
    State Cost: $1,500,000.00
    Total Cost: $7,500,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/27/2023
    Project Need Form PNF Approved 02/26/2023
    Project Initiation Form PIF Entered 02/27/2023
    Project Initiation Form PIF Approved 02/26/2023
    Project Initiation Form PRC Submitted 02/27/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Management