| Project Description: |
WORCESTER- BRIDGE PRESERVATION OF 11 STRUCTURES ON I-190 AND RAMPS
Work consists of cleaning & painting of structural steel on bridges W-44-124 (1XF, 1XG), W-44-126 (1XJ, 1XK), W-44-127 (1XL), W-44-132 (1XN, 1XP), and W-44-133 (1XQ, 1XR) in the town of Worcester.
|
| Location: |
|
| Construction Begins: | Autumn 2025 |
| Resident Engineer: | Kevin Troy![]() |
| Construction Bid Price: | $12,836,355.90 |
| District: | District 3 |
|
Bridges
|
||||||||
|
||||||||||
|
|
|
|||||||||||||||||||||||||||||||||||||||||||||||