Project Description:
WORCESTER- BRIDGE PRESERVATION OF 11 STRUCTURES ON I-190 AND RAMPS
Work consists of cleaning & painting of structural steel on bridges W-44-124 (1XF, 1XG), W-44-126 (1XJ, 1XK), W-44-127 (1XL), W-44-132 (1XN, 1XP), and W-44-133 (1XQ, 1XR) in the town of Worcester.
Location:
  • City of Worcester
  • Construction Begins: Autumn 2025
    Resident Engineer: Kevin Troy
    Construction Bid Price: $12,836,355.90
    District: District 3

    Contracts (1) Progress
    # 130787 -- Construction Contract
    Bridge Preservation of 11 Structures on I-190 and Ramps

    Bridges

    Contract Dates
    Notice to Proceed: 10/17/2025
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/27/2023
    Project Need Form PNF Approved 02/26/2023
    Project Initiation Form PIF Entered 02/27/2023
    Project Initiation Form PIF Approved 02/26/2023
    Project Initiation Form PRC Submitted 02/27/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Status Advertised 06/21/2025
    Project Management
    100% Design 100% Package Received 03/21/2025
    100% Design 100% Package Comments to DE 04/09/2025
    75% Design 75% Package Received 11/08/2024
    75% Design 75% Package Comments to DE 03/11/2025
    Final Design PS&E Received 05/07/2025
    Final Design PS&E Received - Resub 1 05/23/2025