BOSTON- BRIDGE PRESERVATION, B-16-236 (39M, 39P, 39U, 39W, 39Y), 5 BRIDGES CARRYING STATE ROUTE 1A (EAST BOSTON EXPRESSWAY NB/SB) AND RAMPS
The project involves preserving bridges B-16-236 (39M, 39P, 39U, 39W, and 39Y) on State Route 1A (East Boston Expressway) and its ramps in East Boston, Massachusetts. The main goal is to replace bridge joints, repair deteriorated concrete near the joints, and patch the existing exterior barriers along Route 1A northbound, the off-ramp, and relevant approaches. Additional repairs include replacing the wearing surface and waterproofing membrane, as well as deck and end diaphragm repairs over Route 1A northbound and the off-ramp.
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2025
    Project Manager: Alyson Bedard
    Estimated Total Contract Cost: $7,870,661.74
    Estimated Total Federal Participating Construction Cost: $6,634,552.50
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: 75% Package Comments to DE (as of 09/27/2024 )

    Contracts (1) Progress
    # 115784 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BOSTON
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $5,220,000.00
    State Cost: $1,305,000.00
    Total Cost: $6,525,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/27/2023
    Project Need Form PNF Approved 02/27/2023
    Project Initiation Form PIF Entered 02/27/2023
    Project Initiation Form PIF Approved 02/27/2023
    Project Initiation Form PRC Submitted 02/27/2023
    Project Review Committee PRC Approved 03/01/2023
    Project Management
    25% Design 25% Package Received 08/23/2024
    75% Design 75% Package Received 08/23/2024
    75% Design 75% Package Comments to DE 09/27/2024
    Consultant Contract Process Scope to DE 11/13/2023
    Consultant Contract Process NTP Issued 12/06/2023