Project Description:
MEDFORD- BRIDGE PRESERVATION OF 10 BRIDGES CARRYING I-93
Bridge preservation of substructures requiring patching in Medford. Topside repairs being completed by other contract this will maintain state of good repair.
Location:
  • City of Medford
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2024
    Project Manager: Alyson Bedard
    Estimated Total Contract Cost: $4,214,265.75
    Estimated Total Federal Participating Construction Cost: $4,572,999.00
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: 75% Package Comments to DE (as of 03/13/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: MEDFORD
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • TFPC: $1,746,000 (HIP-BR)
  • Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $1,396,800.00
    State Cost: $349,200.00
    Total Cost: $1,746,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/27/2023
    Project Need Form PNF Approved 02/27/2023
    Project Initiation Form PIF Entered 02/27/2023
    Project Initiation Form PIF Approved 02/27/2023
    Project Initiation Form PRC Submitted 02/27/2023
    Project Review Committee PRC Approved 03/01/2023
    Project Management
    75% Design 75% Package Received 02/09/2024
    75% Design 75% Package Comments to DE 03/13/2024
    Consultant Contract Process NTP Issued 09/27/2023