BECKET- BLANDFORD- STOCKBRIDGE- WEST STOCKBRIDGE- BRIDGE PRESERVATION OF B-03-061 (4FX), B-03-062 (4FW), B-14-021 (4G6), S-26-014 (4H3), W-22-023 (4HG), AND W-22-026 (4HF)
The project is a bridge preservation job addressing overpass bridges on the I-90 corridor. The six bridges to be repaired will be in the towns of Becket (Werden Rd, Johnson Rd), Blandford (Old Chester Rd), Stockbridge (Prospect Hill Rd), and West Stockbridge (Baker St). A combination of deck, superstructure, and substructure repairs will be conducted to restore the bridges to a state of good repair.
Location:
  • Town of Becket
  • Town of Blandford
  • Town of Stockbridge
  • Town of West Stockbridge
  • Construction Begins: Winter 2023/2024
    Resident Engineer: Alexandra Campos-Castillo
    Construction Bid Price: $11,987,167.00
    District: District 1

    Contracts (2) Progress
    # 115745 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 124620 -- Construction Contract
    Bridge Preservation of B-03-061 (4FX), B-03-062 (4FW), B-14-021 (4G6), S-26-014 (4H3), W-22-023 (4HG), and W-22-026 (4HF) 1% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 02/28/2024
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/28/2023
    Project Need Form PNF Approved 02/28/2023
    Project Initiation Form PIF Entered 02/28/2023
    Project Initiation Form PIF Approved 02/28/2023
    Project Initiation Form PRC Submitted 04/19/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Status Advertised 11/11/2023
    Project Management
    100% Design 100% Package Received 08/31/2023
    100% Design 100% Package Comments to DE 09/18/2023
    Final Design PS&E Received 10/06/2023
    Final Design PS&E Received - Resub 1 10/26/2023