Project Description:
BEDFORD- BILLERICA- CHELMSFORD- TYNGSBOROUGH- BRIDGE PRESERVATION OF 41 BRIDGES IN ROUTE 3 CORRIDOR
This project will perform minor concrete patching to the existing bridge components as well as joint replacement on 41 bridges carrying Route 3 from the NH line to the town of Bedford.
Location:
  • Town of Bedford
  • Town of Billerica
  • Town of Chelmsford
  • Town of Tyngsborough
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2024
    Project Manager: Genesis Poz Diaz
    Estimated Total Federal Participating Construction Cost: $9,966,776.75
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Northern Middlesex Metropolitan Planning Organization.
    District: District 4
    Current Status: 100% Package Comments to DE (as of 04/19/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Northern Middlesex Metropolitan Planning Organization
    Location: Municipality
    Cities: BEDFORD
    BILLERICA
    CHELMSFORD
    TYNGSBOROUGH
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $7,999,400.00
    State Cost: $1,999,850.00
    Total Cost: $9,999,250.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/28/2023
    Project Need Form PNF Approved 02/28/2023
    Project Initiation Form PIF Entered 02/28/2023
    Project Initiation Form PIF Approved 02/28/2023
    Project Initiation Form PRC Submitted 02/28/2023
    Project Review Committee PRC Approved 03/01/2023
    Project Management
    100% Design 100% Package Received 03/15/2024
    100% Design 100% Package Comments to DE 04/19/2024
    75% Design 75% Package Received 12/22/2023
    75% Design 75% Package Comments to DE 01/23/2024
    Consultant Contract Process NTP Issued 08/09/2023