Project Description:
MARLBOROUGH- BRIDGE PRESERVATION, M-06-010, ELM STREET OVER I-495
This project will consist of deck patching, replacement of joints, and replacement of the wearing surface.
Location:
  • City of Marlborough
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2025
    Project Manager: Genesis Poz Diaz
    Estimated Total Contract Cost: $2,398,631.50
    Estimated Total Federal Participating Construction Cost: N/A
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 3
    Current Status: PS&E Received (as of 05/02/2025 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: MARLBOROUGH
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $1,728,000.00
    State Cost: $432,000.00
    Total Cost: $2,160,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/02/2023
    Project Need Form PNF Approved 03/02/2023
    Project Initiation Form PIF Entered 03/02/2023
    Project Initiation Form PIF Approved 03/02/2023
    Project Initiation Form PRC Submitted 03/13/2023
    Project Review Committee PRC Approved 06/01/2023
    Project Management
    100% Design 100% Package Received 04/07/2025
    100% Design 100% Package Comments to DE 04/23/2025
    75% Design 75% Package Received 02/24/2025
    75% Design 75% Package Comments to DE 03/24/2025
    Final Design PS&E Received 05/02/2025