Project Description: |
CHICOPEE- HOLYOKE- NORTHAMPTON- SPRINGFIELD- WEST SPRINGFIELD- BRIDGE PRESERVATION OF 26 BRIDGES ALONG I-91
This project will comprise of deck, superstructure, and substructure repairs in kind to restore bridges to state of good repair. The project limits are from the I-91 crossing over B&M Railroad/US-5/SR 10 in
Northampton (northern limit) to the US-20 crossing at I-91 in Springfield (southern limit).
|
Location: |
|
Design Responsibility: | In-House Boston |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Spring 2025 |
Project Manager: | Albin Napit |
Estimated Total Contract Cost: | $11,137,500.00 |
Estimated Total Federal Participating Construction Cost: | $11,550,000.00 |
Funding Provision: | This project is planned to be funded through the 2025 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization. |
District: | District 2 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
|
|
|