Project Description:
DISTRICT 5- VEGETATION MANAGEMENT (MECHANICAL) AT VARIOUS LOCATIONS (EXCLUDING THE ISLANDS)
Work will involve the removal of overgrowth to expose signage, improve visibility and to provide more frequent mowing on targeted District locations.
Location:
Construction Begins: Spring 2024
Resident Engineer: Joseph Goncalves
Construction Bid Price: $1,494,680.00
District: District 5

Contracts (1) Progress
# 125316 -- Construction Contract
Vegetation Management (Mechanical) at Various Locations (Excluding the Islands)

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/12/2024
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/03/2023
    Project Need Form PNF Approved 04/03/2023
    Project Initiation Form PIF Entered 04/03/2023
    Project Initiation Form PIF Approved 04/03/2023
    Project Initiation Form PRC Submitted 04/11/2023
    Project Review Committee PRC Approved 07/05/2023
    Project Status Advertised 02/24/2024
    Project Management
    100% Design 100% Package Received 08/29/2023
    Final Design PS&E Received 01/17/2024
    Final Design PS&E to FAPRO 02/02/2024