Project Description:
WESTPORT- BRIDGE PRESERVATION OF W-30-025 (3UD, 3UE), I-195 OVER SANFORD ROAD
Location:
  • Town of Westport
  • Construction Begins: Autumn 2024
    Resident Engineer: Dylan Hipolito
    Construction Bid Price: $1,843,832.25
    District: District 5
    Current Status: The contractor has complete bridge deck milling, partial depth concrete excavation, and hydro-demolition operations during phase 1. On-going work consists of full depth concrete excavation, forming/pouring full depth deck repairs, and preparing for the latex modified concrete overlay. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 04/07/2025)

    Contracts (1) Progress
    # 127515 -- Construction Contract
    Bridge Preservation of W-30-025 (3UD, 3UE), I-195 over Sanford Road

    Bridges

    Contract Dates
    Notice to Proceed: 10/04/2024
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    The contractor has complete bridge deck milling, partial depth concrete excavation, and hydro-demolition operations during phase 1. On-going work consists of full depth concrete excavation, forming/pouring full depth deck repairs, and preparing for the latex modified concrete overlay. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/03/2023
    Project Need Form PNF Approved 04/03/2023
    Project Initiation Form PIF Entered 04/03/2023
    Project Initiation Form PIF Approved 04/03/2023
    Project Initiation Form PRC Submitted 04/03/2023
    Project Review Committee PRC Approved 04/12/2023
    Project Status Advertised 08/03/2024
    Project Management
    75% Design 75% Package Received 04/16/2024
    75% Design 75% Package Comments to DE 05/31/2024
    Final Design PS&E Received 06/14/2024
    Final Design PS&E Received - Resub 1 07/11/2024