Project Description:
WESTBOROUGH- ROADWAY IMPROVEMENTS ON ROUTE 30 (EAST MAIN STREET), FROM HASTINGS ELEMENTARY TO THOMAS NEWTON DRIVE
The proposed project includes roadway improvements on Route 30 from Hastings Elementary School to Thomas Newton Drive, a distance of 1.2 miles. The improvements include intersection improvements at Flanders Road as well as improved bike and pedestrian accommodations. Related work includes upgrades to signage, drainage and pavement markings.
Location:
  • Town of Westborough
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2029
    Project Manager: Jonathan E Freeman
    Estimated Total Contract Cost: $8,447,389.81
    Estimated Total Federal Participating Construction Cost: $8,824,848.70
    Funding Provision: This project is planned to be funded through the 2029 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2029
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: WESTBOROUGH
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $10,236,825, Design Status = Approved, YOE = 16%, PM Score = 15 out of 27
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $8,189,460.00
    State Cost: $2,047,365.00
    Total Cost: $10,236,825.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/04/2023
    Project Need Form PNF Approved 11/29/2022
    Project Initiation Form PIF Entered 04/04/2023
    Project Initiation Form PIF Entered 10/31/2023
    Project Initiation Form PIF Approved 02/23/2023
    Project Initiation Form PRC Submitted 04/11/2023
    Project Initiation Form PRC Submitted 10/31/2023
    Project Review Committee PRC Tabled 06/01/2023
    Project Review Committee PRC Approved 10/31/2023
    Project Management